George Weston Food Ham Slicing Line Installation

George Weston Foods Ham Slicing Line Installation

Project Background

George Weston Foods is one of Australia and New Zealand’s largest food manufacturers with

DON Foodservice as a prominent supplier of authentic smallgoods to the Australian hospitality industry. The Don KR Castlemaine facility is state-of-the-art and is the largest single-site employer in Victoria. Pro Services is DON’s primary contractor for mechanical installations across all sites.

Services

Pro Services provided a comprehensive range of services to install a new Ham Slicing Line. This included maintenance fitters, fabricators and an installation crew. The services included custom designs and fabrication, competitively priced against European mechanical services.

Challenges

Delays due to equipment being held in port had set installation back by approximately two weeks. To reduce the impact of this delay, Pro Services fast tracked the 4-day installation originally scheduled and completed the work in approximately 2 days. This required weekend work and additional shifts to ensure readiness for commissioning on the following Monday.

 

Access to the factory posed a challenge as it remained operational throughout the installation process. Pro Services used problem solving and critical thinking to minimise shutdown time and coordinate effectively with DON’s operations.

Project Outcome

Despite the scheduling and timeframe challenges, the Ham Slicing Line was successfully installed ready for commissioning as specified. The factory stayed operational with no impact on other lines and no production downtime.

Timeframe

The initial timeframe for the project was reduced by one full day, requiring the introduction of a second shift to meet the revisited timeline. Pro Services coordinated a 24-hour shift to ensure the production deadlines were met.

Customer Benefit

The ultimate benefit to DON Foodservice and its clients was the timely completion of the Ham Slicing Line Installation. Despite unforeseen delays and challenges, Pro Services’ project management and adaptability ensured minimal disruption to operations. This timely installation enabled DON to enhance its production capabilities and meet customer demand.

Testimonial

“Pro Services has always been able to accommodate our constraints and safety regulations. This project was a five-day installation with dangerous equipment involved and because of the resources Pro Services could provide, we worked around the clock doing shift work to get it done in 2 days. I don’t know another company who could have made that work.”

 

“The quality of work Pro Services provides is always unmatched. They have competitive pricing, local workers, plenty of resources, great communication, and the company is engaging and helpful. No project is rushed, and they always take the time to maintain safety protocols.”

 

Brett Struhs

Project Manager